Safelane used on M25
Case Study: M25 Newhall Joint Replacement Scheme
Jacksons used Safelane on the M25 for the Newhall Joint Replacement Scheme. The scheme was to replace a multi-element expansion joint between junctions 10 and 11 on M25 clockwise and anti-clockwise.

As the main contractor, Jacksons asked Highway Resource Solutions to design a Safelane system for a full carriageway closure on M25 anti-clockwise.
Jacksons crews were surprised by how easy Safelane was to install, having been weary of it to begin with, they soon had a complete change of heart.
Karen Doherty, Systems Engineer commented:
“The TM crew felt that the training course they undertook before using Safelane was really good, and it gave them the knowledge they needed to go out and install it."